After winning, a number of construction teams moved in construction. By road from Longkou Tianhe North Road all the way south to dig. Some lived in nearby residents said recently over three months, this road has been in a state of excavation and construction, construction progress is extremely slow.
Dexin district, Liede area rain and sewage diversion and other improvement systems engineering (Central) project is the central city rain and sewage projects,http://billtran-moo.seesaa.net,Louboutin Homme, according to the Tianhe district government arrangements, Longkou West Road intersection segment excavation and construction in July for examination,http://huimengmall.com/news/html/?5635.html, 7 March 16, after the excavation approval to begin Longkou West Zhongshan Road junction to the construction segment drains. Program, as amended, and no elevation of one meter situation can not be connected. Construction unit part of the staff did not seriously study the drawings, verification site, there is an error,http://www.wearmydiveart.com, and thus delayed nearly three weeks of construction time. Construction costs will increase by about 400,000 yuan more than the original construction methods, which can be charged from behind in the gold project. Tianhe District PMO has to seize urge the construction units in accordance with the design and construction,Louboutin Bottines, and to strengthen the management and communication, to ensure the completion of September 30. (Correspondent Tian)
Longkou West rain sewage diversion project belongs Dexin district, Liede area and other part of the system of rain and sewage improvement project. According to the relevant person in charge of the construction side, he said the total project cost of more than 5,700 yuan, the Guangzhou municipal finance investment at the end of January this year began to open tender.
When the closure of the pipeline was found not on the butt
"Pipeline under the complex and often worried dig burst water pipe or cable." A staff member complained operating digging machines. He said that the project is complex, first drilling pavement, and then the excavator 2 m deep trenches, then put the diameter of 1 & nbsp; .5 meters of the outfall landfill, cleared away immediately after the completion of the formation of sludge and pavement.
Construction unit personnel are not serious and wrong
Longkou West to two lanes,http://bbs.aizbc.com/forum.php?mod=viewthread&tid=288636&fromuid=25405,Louboutin Souliers Plat, one lane is closed during construction, one to the rush hour,http://211.86.128.2/gjjl/Review.asp?NewsID=595, the road is congested. "All day stuck in the intersection, the road turns into the area from the Milky Way at least to 20 minutes." Lived in Regal Court district of Miss Tan said.
Southern News reporter Zhang Hao cost of more than 5700 million Longkou West rain sewage diversion project recently embarrassed. When Longkou West Road all the way south along the excavation for several months near the ending, workers accidentally found embedded in the butt Tianhe Road pipeline under construction digging more than the current pipeline of nearly one meter. In half a month after the suspension, re-planning of construction engineering department lines.
"It is a waste of taxpayers' money in." In the time before the interview, the provincial CPPCC Standing Committee MENG Hao had commented.
 ,http://gongsi.folieyun.com/forum.php?mod=viewthread&tid=209661;
Half-million yuan investment project, why there dug a few months only to find not on the butt Liu 付亚富 engineering construction side Guangzhou City construction of municipal engineering manager, said at the interface Tianhe Road, was previously reserved for other construction units, the emergence of this situation they are unexpected.
 ,http://kmbhwl.com/home.php?mod=space&uid=2592;
■ official description
However, in early August,http://abc168.66rt.com/viewthread.php?tid=449690&extra=, when the project is located near the ending of the accident found embedded at Tianhe Road before docking pipeline than dig Longkou West pipeline was nearly one meter. "By design,Louboutin Sandales, the sewage flows along the pipeline from Longkou West Tianhe Road, there are so many high,Louboutin Pas cher, you can not dock." Scene of a worker he said.
Residents worried about the problem while sewage discharge. Because the pipeline not on the butt, sewage accumulated in the pipe outlet did not break out, it will appear after the intrusion of rain in some places.
Sewer situation arises not on the butt, the site is located in Tianhe Road junction of half a month's time in a suspended state. Reporters on the scene saw recently, no construction workers on site, any site did not stick with the project-related notices.
Roads blocked sewage intrusion neighborhood worry |
|